Force Majeure in Property Contracts in Dubai: Legal Meaning, Risks, and Remedies

Force Majeure in Property Contracts in Dubai: Legal Meaning, Risks, and Remedies

Force Majeure in Property Contracts in Dubai: 9 Essential Legal Rules for Safer Property Deals

Force Majeure in Property Contracts in Dubai: 9 Essential Legal Rules and Remedies

Force majeure can become a critical issue when an unexpected event disrupts a property transaction, construction programme, handover date, lease, development obligation or other contractual commitment. For anyone dealing with force majeure in property contracts in Dubai, the important question is not simply whether an extraordinary event occurred. The parties must consider whether the event falls within the applicable contract and law, whether it actually affected performance, whether performance became impossible or merely more difficult, and what evidence and notice requirements apply.

This is particularly important in 2026 because the UAE’s civil-law framework has changed. Federal Decree by Law No. 25 of 2025 promulgating the new Civil Transactions Law entered into force on 1 June 2026 and repealed Federal Law No. 5 of 1985. Under the new framework, Article 236 addresses force majeure and the consequences of impossibility.

If you are dealing with a delayed property transaction, construction project or disputed contractual obligation, a review of the SPA, lease, development agreement and applicable legislation should come before assuming that force majeure applies.

For broader guidance, visit our real estate lawyer in Dubai resources and related property-law guides.

Table of Contents

Quick Answer: What Does Force Majeure in Property Contracts in Dubai Mean?

Force majeure in property contracts in Dubai generally concerns an external event that makes contractual performance impossible, subject to the applicable law and contractual terms.

Under the new UAE Civil Transactions Law, Article 236 addresses situations in which force majeure makes performance of an obligation under a bilateral contract impossible. The legal consequences can differ where the impossibility is total, partial or temporary.

This means:

  • An extraordinary event alone is not enough.
  • The affected obligation must be examined.
  • There must be a meaningful connection between the event and the inability to perform.
  • Contract wording remains important.
  • Notice and evidence requirements may apply.
  • A delay that is merely inconvenient, expensive or commercially difficult is not necessarily force majeure.
  • Hardship or exceptional circumstances may provide a different legal route where performance remains possible but becomes excessively onerous.

For a buyer, developer, landlord or tenant, the practical issue is therefore to identify what happened, what obligation was affected, why it could not be performed, and what the contract and applicable law actually provide.

1. What Is Force Majeure in Property Contracts in Dubai?

Force majeure in property contracts in Dubai describes circumstances outside the affected party’s reasonable control that prevent contractual performance, subject to the legal regime governing the agreement.

Examples can include:

  • Natural disasters
  • Certain government restrictions
  • War or serious civil disturbance
  • Extraordinary public emergencies
  • Events specifically covered by the contract
  • Other external events capable of satisfying the applicable legal test

However, listing an event in a contract does not automatically establish a force majeure defence.

The real issue is causation and effect.

For example, if a developer claims that a government restriction prevented construction for three months, the parties may need to examine:

  1. What restriction was imposed?
  2. When did it begin?
  3. Which construction activities did it actually prevent?
  4. Could other work have continued?
  5. Did the restriction affect the critical path of the project?
  6. Were reasonable mitigation measures taken?
  7. Does the contract permit an extension for that particular event?
  8. Was contractual notice given correctly?

That evidence-based approach is much more useful than simply describing an event as “force majeure.”

2. What Changed Under UAE Law in 2026?

A major update should be reflected in any current article about force majeure in property contracts in Dubai.

The new UAE Civil Transactions Law, Federal Decree by Law No. 25 of 2025, entered into force on 1 June 2026 and repealed Federal Law No. 5 of 1985. The new law places force majeure and impossibility under Article 236.

The previous Civil Transactions Law dealt with force majeure under Article 273. The new law should therefore be used when analysing matters governed by the legislation in force from 1 June 2026.

For the primary legislation, readers should consult the official UAE Legislation portal and the text of Federal Decree by Law No. 25 of 2025.

Article 236: Why It Matters

Under Article 236, where force majeure makes performance of an obligation under a bilateral contract impossible, the corresponding obligation is extinguished and the contract may be rescinded by operation of law.

The consequences can differ depending on whether the impossibility is:

  • Total
  • Partial
  • Temporary

This means force majeure in property contracts in Dubai should not be analysed solely by asking whether an extraordinary event occurred. The nature and extent of the resulting impossibility also matter.

3. Force Majeure Is Different From Hardship

One of the most important distinctions in force majeure in property contracts in Dubai is the difference between impossibility and hardship.

Force majeure

The relevant obligation cannot be performed because of the extraordinary event.

Hardship or exceptional circumstances

Performance remains possible, but circumstances arising after the contract was made may make performance exceptionally onerous and threaten the contractual balance.

The new Civil Transactions Law separately addresses exceptional circumstances. Current legal commentary identifies Article 224 as the principal provision concerning this type of relief, while Article 236 addresses force majeure and impossibility.

This distinction matters in property disputes.

For example:

Scenario A — possible force majeure:
A government order legally prevents a specific contractual performance and the obligation cannot be performed while the restriction remains in effect.

Scenario B — possible hardship:
Construction remains legally possible, but extraordinary circumstances cause major increases in costs and make performance substantially more burdensome.

The second situation should not automatically be labelled force majeure. Depending on the facts and governing law, hardship or exceptional-circumstances provisions may be more relevant.

4. Does a Force Majeure Clause Automatically Protect a Developer?

No.

A developer cannot safely assume that inserting the words “force majeure” into an SPA automatically eliminates liability for delay.

The contract should be examined for:

  • The definition of force majeure
  • Covered and excluded events
  • Notice deadlines
  • Evidence requirements
  • Causation requirements
  • Mitigation obligations
  • Extension-of-time provisions
  • Delay damages
  • Long-stop dates
  • Termination rights
  • Refund provisions
  • Dispute-resolution provisions

The same principle applies to purchasers.

A buyer cannot necessarily rely on a general force majeure clause to cancel an SPA simply because circumstances have become difficult.

The contractual mechanism and applicable legislation must be considered together.

If the dispute involves broader contractual rights or a property disagreement, see our detailed guide to property disputes in Dubai.

5. How Does Force Majeure in Property Contracts in Dubai Affect Off-Plan Property?

Off-plan transactions require particular care because construction delay, regulatory supervision, escrow arrangements and SPA obligations can interact.

The Dubai Land Department and RERA have a specific regulatory framework for off-plan projects. DLD’s regulatory framework covers developers selling real estate off-plan in Dubai and provides mechanisms for monitoring project progress and dealing with delayed or cancelled projects.

For an off-plan buyer, a developer’s force majeure claim should therefore be considered alongside:

  • The SPA
  • Project registration
  • Construction progress
  • RERA/DLD records
  • Escrow arrangements
  • Approved project information
  • Contractual completion dates
  • Extension provisions
  • Notice correspondence
  • The actual cause of delay

Dubai’s off-plan legislation also contains specific rules concerning circumstances beyond a developer’s control and procedures connected with termination and refunds.

This is why a developer’s statement that “the project was delayed because of force majeure” should not be treated as the end of the analysis.

If the project itself is delayed or cancelled, our guide to cancelled real estate projects in Dubai provides additional context.

6. What Is Not Usually Enough to Establish Force Majeure in Property Contracts in Dubai?

A party should be careful about treating ordinary commercial difficulties as force majeure.

Depending on the governing contract and applicable law, examples that may not satisfy the force-majeure test include:

  • Ordinary market fluctuations
  • Poor financial planning
  • Lack of financing
  • Cash-flow problems
  • Increased construction costs
  • Ordinary supply difficulties
  • Poor project management
  • Contractor disputes that could reasonably have been managed
  • Internal administrative problems
  • A commercial decision to delay performance
  • A general reduction in profitability

The key distinction is between impossibility and increased difficulty.

In other words, force majeure in property contracts in Dubai is not simply a legal label that can be attached to any commercially difficult situation.

A party should be able to explain why the event prevented the specific contractual performance at issue.

7. What Notice and Evidence Should Be Provided for Force Majeure in Property Contracts in Dubai?

A party relying on force majeure should check the contract immediately for its notice requirements.

A strong notice may identify:

  • The event relied upon
  • The date the event occurred
  • The contractual clause being invoked
  • The affected obligation
  • The precise impact on performance
  • The expected duration
  • Supporting documents
  • Mitigation measures
  • Revised completion expectations
  • Any relief requested

Useful evidence may include:

  • Government orders
  • Official notices
  • Project records
  • Construction reports
  • Engineer or consultant reports
  • Correspondence with contractors
  • Delivery records
  • Site reports
  • Photographs
  • Programme updates
  • Financial or operational records where relevant

A vague email saying that an “unforeseen event” caused delay may be substantially weaker than a properly documented contractual notice.

8. Can Force Majeure in Property Contracts in Dubai Terminate a Property Contract?

Potentially, but termination should never be assumed merely because a force majeure event has occurred.

Under Article 236 of the new UAE Civil Transactions Law, the legal consequences depend in part on whether performance has become impossible and whether the impossibility is total, partial or temporary.

The contract may also contain its own:

  • Termination mechanism
  • Long-stop date
  • Notice period
  • Refund provisions
  • Extension period
  • Dispute-resolution procedure

For off-plan property, additional Dubai real-estate legislation can affect termination and refund procedures.

A buyer should therefore avoid signing a termination agreement, accepting a revised handover date or abandoning payments solely on the assumption that force majeure in property contracts in Dubai has already determined the parties’ rights.

9. What Should a Buyer Do When a Developer Claims Force Majeure in Property Contracts in Dubai?

If a developer invokes force majeure, the buyer should move from a general complaint to an evidence-based contractual review.

Step 1: Obtain the contractual clause

Identify the exact SPA provision relied upon.

Step 2: Request the factual basis

Ask what event occurred and when.

Step 3: Test causation

Determine how the event actually affected the project and whether it caused the specific delay claimed.

Step 4: Check the project record

Compare the developer’s explanation with available DLD/RERA project information and construction progress.

Step 5: Check notice compliance

Review whether the developer complied with the SPA’s notice and evidence requirements.

Step 6: Check alternative causes

Look for evidence of financing, approval, contractor, procurement, planning or other issues that may have contributed to the delay.

Step 7: Review your contractual remedies

Depending on the agreement and applicable law, possible remedies may include:

  • Extension of time
  • Contractual compensation
  • Enforcement of contractual obligations
  • Negotiated settlement
  • Termination where legally available
  • Refund claims where applicable
  • Court or other dispute-resolution proceedings

The appropriate remedy depends on the contract, facts, governing law and applicable Dubai real-estate regulations.

Force Majeure vs Hardship vs Ordinary Delay

SituationBasic issuePossible legal treatment
Force majeurePerformance becomes impossible because of an extraordinary external eventArticle 236 and applicable contractual provisions may become relevant
Hardship / exceptional circumstancesPerformance remains possible but becomes exceptionally onerousSeparate statutory and contractual relief may need consideration
Ordinary delayPerformance remains possible but is lateContractual delay provisions and remedies may apply
Financial difficultyParty cannot economically performNot automatically force majeure
Poor planningDelay results from avoidable project management issuesRequires separate contractual/legal analysis
Temporary impossibilityPerformance cannot occur temporarilyArticle 236’s treatment of temporary impossibility may become relevant

What Should a Force Majeure Clause in a Dubai Property Contract Contain?

A carefully drafted clause should ideally address more than a list of disasters.

Before signing, consider whether the clause clearly addresses:

Definition

What events qualify?

Causation

Must the event actually prevent or materially affect performance?

Notice

How quickly must the affected party notify the other party?

Evidence

What documents must be supplied?

Mitigation

What steps must the affected party take to reduce the impact?

Time extension

How is the extension calculated?

Long-stop date

When can the unaffected party terminate if disruption continues?

Payment obligations

Which payment obligations continue during the event?

Delay damages

Are liquidated damages suspended, reduced or otherwise affected?

Termination

When can either party terminate?

Refunds

What happens to money already paid?

Dispute resolution

Which court, tribunal or dispute mechanism applies?

These provisions can significantly reduce uncertainty when a serious disruption occurs.

Common Force Majeure Mistakes in Dubai Property Disputes

Mistake 1: Treating every delay as force majeure

A delay is a factual event. Whether it legally qualifies as force majeure requires further analysis.

Mistake 2: Ignoring the governing law

An onshore Dubai contract and a contract governed by a different legal regime should not automatically be analysed in the same way.

Mistake 3: Relying only on the contract clause

Statutory provisions may also affect the parties’ rights and remedies.

Mistake 4: Ignoring causation

The event must be connected to the inability to perform the relevant obligation.

Mistake 5: Confusing hardship with impossibility

A contract becoming more expensive or commercially difficult does not automatically mean performance is impossible.

Mistake 6: Failing to preserve evidence

Project records, correspondence, notices and technical reports may become important if the dispute reaches mediation, arbitration or court proceedings.

Mistake 7: Accepting an indefinite extension

A buyer should understand whether an extension has a defined end date and what happens if the delay continues.

How a Property Lawyer Can Help With Force Majeure in Property Contracts in Dubai

A specialist property lawyer can review the dispute from both the contractual and regulatory perspectives.

Depending on the circumstances, legal assistance may include:

  • Reviewing the SPA or property contract
  • Identifying the applicable force majeure provision
  • Checking the governing law
  • Assessing the evidence supporting the claimed event
  • Analysing causation
  • Reviewing contractual notice compliance
  • Comparing contractual deadlines with actual project progress
  • Assessing potential termination rights
  • Reviewing refund or compensation provisions
  • Preparing a formal legal notice
  • Negotiating an extension or settlement
  • Advising on dispute-resolution options
  • Representing the client in property-related proceedings where appropriate

For more information about the role of legal counsel, see the role of lawyers in property litigation in Dubai and our guide to hiring a property lawyer in Dubai.

If you are researching force majeure in property contracts in Dubai, these related resources can help you assess the wider legal context:

Practical Checklist: Force Majeure Claim in a Dubai Property Contract

Before accepting or challenging a force majeure claim, check:

  • What exact event occurred?
  • Was the event outside the affected party’s control?
  • Was the event foreseeable when the contract was signed?
  • Did it actually prevent contractual performance?
  • Was performance impossible or merely more expensive?
  • Does the contract expressly cover the event?
  • Was notice given within the required period?
  • Has supporting evidence been provided?
  • Were reasonable mitigation measures taken?
  • Did other causes contribute to the delay?
  • What does the SPA say about extensions?
  • Is there a long-stop date?
  • What happens to delay damages?
  • Are termination rights triggered?
  • Do Dubai off-plan regulations affect the dispute?
  • What happens to amounts already paid?
  • What dispute-resolution mechanism applies?
  • Which version of UAE legislation governs the contract?

Frequently Asked Questions

Is force majeure in property contracts in Dubai automatic?

Not simply because an extraordinary event occurs. The applicable legislation, contractual wording, nature of the event, causal connection and effect on performance must be considered.

For current contracts governed by the UAE’s onshore civil-law framework, Article 236 of the new Civil Transactions Law is particularly relevant where force majeure makes performance impossible.

Can a developer use force majeure to justify any construction delay?

No. A developer’s assertion does not by itself establish a valid force majeure defence. The actual event, its impact on construction, contractual wording, evidence, notice and applicable Dubai real-estate regulations should be examined.

Does increased construction cost qualify as force majeure?

Not automatically. Increased cost generally raises a different question from objective impossibility. Depending on the circumstances, exceptional-circumstances or hardship provisions may be more relevant than force majeure.

Can a buyer cancel an off-plan SPA because of force majeure?

Not automatically. Cancellation depends on the SPA, applicable legislation, the nature and duration of the disruption, project status and the remedies available under the applicable regulatory framework.

Does force majeure mean the developer can delay handover indefinitely?

No general rule permits an indefinite delay simply because force majeure has been invoked. The contract, evidence, applicable law and project-specific circumstances must be assessed.

What is Article 236 of the UAE Civil Transactions Law?

Article 236 of the new UAE Civil Transactions Law addresses force majeure where performance of an obligation under a bilateral contract becomes impossible. It also provides different treatment for partial and temporary impossibility.

What happened to Article 273?

Article 273 belonged to the former UAE Civil Transactions Law. Federal Decree by Law No. 25 of 2025 repealed the former law from 1 June 2026 and introduced the new Civil Transactions Law, with Article 236 addressing force majeure.

Does RERA decide every force majeure dispute?

No. DLD/RERA have important regulatory functions concerning Dubai real estate and off-plan projects, but whether a contractual obligation is enforceable, terminated or subject to another remedy can depend on the applicable contract, legislation and dispute-resolution forum.

Should I stop making payments if a developer claims force majeure?

Do not assume that a force majeure dispute automatically suspends your payment obligations. The SPA, applicable law and any valid contractual or legal relief should be reviewed before withholding payment.

Can a force majeure dispute be negotiated?

Yes. Depending on the circumstances, parties may negotiate an extension, revised performance schedule, settlement, termination arrangement or other solution. Any settlement should be documented carefully and checked for consistency with the governing contract and applicable law.

Official and Authoritative Resources

For readers who want to verify the underlying framework, useful primary or authoritative resources include:

Final Takeaway: Force Majeure Is About the Effect of the Event, Not Just the Event Itself

Force majeure in property contracts in Dubai should be analysed carefully rather than treated as a general excuse for delay or non-performance.

The most important questions are:

  1. What event occurred?
  2. What contractual obligation was affected?
  3. Did the event actually make performance impossible?
  4. Is the situation temporary, partial or complete?
  5. What does the contract provide?
  6. Was proper notice given?
  7. What evidence supports the claim?
  8. Could hardship or exceptional circumstances be more appropriate?
  9. What remedies are available under the applicable law and Dubai property regulations?

The 2026 legal framework makes the distinction between force majeure, impossibility and hardship particularly important. Article 236 of the new Civil Transactions Law should therefore be considered alongside the actual contract and any special Dubai real-estate legislation that applies.

If a developer, seller, landlord, tenant or purchaser has invoked force majeure in property contracts in Dubai, obtaining a contract-specific legal review before accepting a revised deadline, withholding performance or terminating the agreement can help clarify the available options.

For further property-law guidance, visit the Dubai real estate lawyer resource hub.

Legal disclaimer: This article provides general information about UAE and Dubai property law and is not a substitute for legal advice on a specific contract or dispute. The applicable law may depend on the date of the agreement, governing-law clause, property type, project status, dispute forum and facts of the case.